    My frame of reference is the latest nuclear reactor built in the US. It was six years late, $14 billion over budget, bankrupted Westinghouse, and is set to increase electric rates. The DoE had to give them a $12 billion loan just to finish construction.

    I’m not scared they’re gonna blow up. I’m scared they’re gonna waste a ton of money that could be used for renewables. Heck, even the small modular reactors are running over cost and over time.

    • Jode@midwest.social
      link
      fedilink
      English
      arrow-up
      5
      arrow-down
      1
      ·
      edit-2
      1 year ago

      Ehhhh Westinghouse bankrupted Westinghouse. They decided they were going to cut Bechtel out of the project and build VC summer by themselves. Pocketing the “savings”. Problem is, the way things had worked for decades before is Westinghouse does the design and Bechtel does the construction. They couldn’t cut it on their own and it destroyed the company. They let the financial dinks speak louder than the engineers and payed for it dearly.

      There’s a chance things would have gone much different if they didn’t try to take on a work scope completely out of their league.

    • Troy@lemmy.caOP
      link
      fedilink
      arrow-up
      2
      ·
      1 year ago

      Just general problems when using lowest bidder based contracting and cost-plus contracts. The same thing happens any time there’s any major project these days: pipelines, transmission lines, hydro plants, etc.

      • Sir_Osis_of_Liver@kbin.social
        link
        fedilink
        arrow-up
        4
        ·
        1 year ago

        The last power plant I worked on was Chinook generating station near Swift Current, a 350MW combined cycle plant for SaskPower. At $605M is was $75M under budget, you will never hear that on a nuclear project.

        The various wind installations are typically fairly close to budget and schedule as well. Hydro is problematic, and that does show in cost overruns, because it is very difficult to predict the geotechnical situation for a given site until excavation starts. Given the stress on the structures, even small differences accumulate rapidly.

        The worst thermal plant projects are consistently nuclear.

        The refurbishment of Lepreau was supposed to cost $1.5B and take 18 months, it ended up taking $2.5B and just under 4 years to complete.

        Flammanville-3 started construction in 2007 was supposed to be operational in 2012. They’re now estimating it will complete commissioning in 2024. Costs have gone from €3.3B to €20B+.

        Olkiluoto-3 started construction in 2005, was supposed to be operational in 2010, but only completed commissioning in 2022. Costs went from €3B to €11B, the not to exceed amount in the contract.

        Hinkley Point C started about 2016, has been pushed back to 2028 and costs have gone from £16B to an estimated £32B.

        Vogtle has been covered, but the V.C Summer plant was no better. Initial estimate was $9B, but the project was cancelled while under construction when the estimated total was projected to exceed $23B.

      • Formes@lemmy.ca
        link
        fedilink
        arrow-up
        4
        ·
        1 year ago

        When you have a firm, that is ran by accountants - odds are, you have a firm that is great at squeezing on line items, but lacks the long term vision to see how that squeeze will lead to deficits and higher cost in the long term.

        The fastest way to plummet a successful company, is to take the Industry experts out of the position (I mean people who worked their way up through the industry, and learned management along the way by experts btw), and replace them with an MBA/ Accountant who got hired into their upper management position without really working in the industry prior to.

        And I pretty much guarantee you, this is what happened.